Hopkins

OPERATING DECEMBER 2022

We are committed to creating a more sustainable future with renewable energy

From corporate buyers to landowners—we prioritize open, honest communication with all our partners. We set realistic expectations on project timelines and maintain strong communication throughout the development, construction, and operation process. Everyone at ENGIE US Grid Scale Renewables genuinely respects our partners, our communities, and our planet, which underpins the work we do every day. We encourage innovation and go the extra mile, every time, to build bigger, better renewable energy projects.

STATUS
In Development
LOCATION
Hopkins County, TX
PROJECT MW
250 MW
TRANSMISSION
ERCOT
PROJECT AREA
1,870+ acres
CUSTOMER
Confidential

Project Timeline

Project Details

REAL ESTATE
  • Over 1,870 acres of land secured under long-term option to lease including all planned solar PV arrays, collection lines, and access roads
  • On-site grid connection – no transmission line needed
INTERCONNECTION
  • Generator interconnection agreement executed in Sept. 2020.
ENVIRONMENTAL
  • Biological Resource Assessment complete
  • Wetlands delineation complete
  • No significant biological constraints or wetland impacts
PERMITTING
  • No discretionary permits required
  • FAA Determination of No Hazard has been obtained
  • Construction Stormwater General Permit is pending
  • US Army Corps wetland permitting pending final design

Engie logo

Let’s talk about your carbon-neutral needs now.

  • Wind
  • Solar
  • Storage
  • Partners
  • Process
  • Why ENGIE?
  • Contact
  • Privacy Policy
Copyright 2020 | All Rights Reserved
  • Wind
  • Solar
  • Storage
  • Partners
  • Process
  • Why ENGIE?
Engie Grid Scale Renewables USA