Our project development and renewables resource teams evaluate potential sites by looking at the solar or wind resource quality, available markets for electricity sales, ability to obtain permits, access to the transmission system, impact on the surrounding environment, current land uses, and project constructability.
Once a potential site is identified, our land agents reach out to landowners. We offer landowners highly competitive payment structures with a long-term revenue stream and advocate for the landowner’s benefit throughout the project development, construction, and operation. We are considerate of our landowner relationships because our projects are only possible through collaboration and honest communication.
We perform extensive studies and surveys to assess the viability of a project site for construction and energy generation. ENGIE cares deeply about the protection of wildlife and habitat. Before a project is built, we conduct numerous environmental impact studies.
Throughout the planning and permitting process, we work with community members as well as local, state, and federal government agencies to ensure compliance with all regulation and requirements. In most cases, environmental and other reports may be part of the development process.
Before a project can be connected to the electricity transmission system, several studies are conducted by the local utility and grid operator to determine if the existing transmission infrastructure can support additional electricity generation. In some cases, equipment upgrades on the system may be required before the project can be constructed, which can pace the construction timeline. Once the studies are complete, an interconnection agreement with the local utility is put in place to let the project connect and transmit power to the electricity grid.
Before a project can be connected to the electricity transmission system, several studies are conducted by the local utility and grid operator to determine if the existing transmission infrastructure can support additional electricity generation. In some cases, equipment upgrades on the system may be required before the project can be constructed, which can pace the construction timeline. Once the studies are complete, an interconnection agreement with the local utility is put in place to let the project connect and transmit power to the electricity grid.
The construction process is generally 9 to 12 months, depending on the project size and weather conditions during construction. This process involves roadwork, grading (if required), underground cabling, foundation setting, equipment installation, and electrical testing and commissioning. After construction, any surrounding property that may have been disturbed during construction is restored to its pre-construction state.
Our first step involves creating a term sheet. The term sheet is not a formal agreement, but rather a general outline of the terms for our contract with a renewable energy customer. We work with our energy customers to discuss their energy needs and propose a customized energy solution that will meet their long-term goals.
Once the energy solution and term sheet have been agreed upon, we detail the rest of the contract structure.
After the contract is finalized, it is approved and signed by both parties—the customer and ENGIE US Renewables.
Throughout the remaining term of the contract, we maintain a reliable, honest, and constant stream of communication with our customers to keep them up to date on their project status. This includes answering questions, providing project photos and videos, organizing site visits and tours, and providing media opportunities.
We are fast acting, innovative, and creative energy solution providers with a tremendous depth of resources, experience, and financial acumen. We’re excited to partner with you to solve your unique sustainability problems to produce creative, effective solutions. Let’s work together to empower communities and create a bright, sustainable future for years to come.
Let’s talk about your carbon-neutral needs now.